§ 5-3-62. Demolition.  


Latest version.
  • An operator who receives notification of a proposed demolition pursuant to section 5-3-52(a) of this article shall ensure clearance for demolition by:

    (1)

    Disconnecting, or causing to be disconnected, as agreed upon by the operator and excavator, all of its utility lines to the structure to be demolished, as well as capping where necessary.

    (2)

    Advising the excavator of the appropriate means of assuring adequate protection for its other utility lines in the vicinity which might be subject to unusual stress during the demolition.

    (3)

    Notifying, or causing to be notified, the excavator that the disconnection has been accomplished or that its utility lines will not be affected by the demolition. (Code 1963, Sec. 39A-23)