§ 5-4-15. Time of validity of erosion and sediment control plans.  


Latest version.
  • (a)

    Any approved erosion and sedimentation control plan shall become null and void 180 days after the date of approval and no further work subject to this chapter shall be allowed unless and until an additional or updated erosion and sediment control plan has been submitted and approved in accordance with the provisions of this chapter or unless all requirements of the approved control plan have been completed in less than 180 days in accord with said plan and verified by an on-site inspection by the director.

    (b)

    When no change in conditions has occurred since the date of approval, an update plan shall be approved in accordance with the provisions of this chapter with no additional requirements. (Ord. No. 4489, 6/16/07, Sec. 1)