§ 5-6-166. Reports of changed discharge.  


Latest version.
  • (a)

    Each user must notify the authority, in writing, of any planned significant changes to the user's operations or system which might alter the nature, quality or volume of its wastewater, at least 30 days prior to the change.

    (b)

    The engineer may require the user to submit such information as may be deemed necessary to evaluate the changed condition, including the submission of a wastewater discharge permit application under section 5-6-141.

    (c)

    The engineer may issue a wastewater discharge permit under section 5-6-141 et seq. or modify an existing wastewater discharge permit in response to changed conditions or anticipated changed conditions.

    (d)

    For purposes of this section, significant changes include, but are not limited to, flow increases of 20 percent or greater, and the discharge of any previously unreported pollutants. (Ord. No. 4501, 10/13/07, Sec. 1)